Phase II Update

J.A. and Kathryn Albertsons Family Foundation Boise River Whitewater Park Phase II – Project Update

Record high water levels in the Boise River this year have affected the next phase of the Whitewater Park. Fall/Winter 2017/2018, the Boise City Parks and Recreation Department (BPR) will focus efforts to repair damaged river bank through the project area.  The Boise River nearly removed a section of bank between the River and Veterans Pond.  This section will need to be reconstructed and armored prior to any additional high water events. 

BPR continues to finalize construction documents and obtain all of the necessary project permits.  The tentative schedule is to begin work on the in-river wave features during the Fall and Winter of 2018/2019.  With a park completion date of June 2019.